What a factory can actually make in a month
A capacity figure without a mix is a number with no meaning. 20,000 chairs is not 20,000 of your chair.
Why the mix matters
Capacity is set by the slowest stage, which is finishing. The factory can machine 5,000 chairs and finish 1,200 if each one needs three coats and a day of cure.
So a mixed order of chairs, tables and booth runs consumes capacity at very different rates.
What to ask
How many of this model, in this finish, in a month, with the current order book. That question gets a real answer; a total capacity figure gets a brochure.
The lines that set the number are described under hotel furniture factory, and the models on hotel dining chairs.
Planning around it
Split large orders into two shipments a month apart so the second one uses the next month's capacity instead of queueing behind the first.
This is in the workshop guide, next to production slots and booking and kiln capacity and scheduling.
Tables compete for the same finishing line — see hotel dining tables.