Kiln capacity is the real production limit
A factory can machine faster than it can dry. That is why the date slips without anyone being late.
The bottleneck
Drying takes weeks, machining takes hours. 8–10% at packing cannot be rushed without leaving stress in the boards, so the kiln sets the pace for everything downstream.
The factory quoting 25–35 days is quoting a kiln schedule that has room in it. One quoting 15 days is quoting timber it already has.
What to ask
How many charges a month, and how much of that is committed. The straight answer tells you whether your order is in the next charge or the one after.
The schedule is described under hotel furniture factory, and the chairs it feeds are on hotel dining chairs.
Where it shows in a rush order
The rushed order is usually timber that was already dry, not timber that dried faster. That is why rush works on standard finishes and fails on a new colour.
This is in the workshop guide, with first article inspection and QC stations and checks as the two notes that follow.
The kiln also feeds table stock, on hotel dining tables.