A delivery window is a promise, a lead time is an estimate
Write the window into the order with a consequence attached, or you have neither.
The difference
Lead time is 25–35 days from sign-off. The window is "on site between 12 and 19 March". The first is a planning number, the second is what the site needs.
The stages that produce it are in lead time stages.
What makes a window hold
The named vessel, a booking made before production ends, and a consequence line. Without the booking the container waits a week at the port and the window is gone.
Suppliers who book before production ends are on hotel dining chairs, and the loading side is in container loading and count.
The consequence line
Liquidated damages at 0.5% per week, capped at 5%. Small enough to be accepted, large enough to make the booking happen.
This is in the buying guide, with rush orders and air freight as the note on the recovery when it slips.
The vessel booking is made at the loading end, in hotel furniture Foshan.