Six stages, and the one that moves is never the one you ask about
25–35 days after sign-off. The variable is the sample queue and the cure time.
The stages
25–35 days after sample sign-off. Drawing and PO 3–5 days, timber release 5–7, machining and assembly 7–10, upholstery 5–8, finishing and cure 3–5, QC and packing 2–3.
Which stage slips in practice is in why samples take longer than promised.
The two variables
The sample, because it queues behind other buyers' samples. And the finish, because a two-pack cure cannot be compressed without failing an adhesion test three weeks later.
Orders that hold the schedule are on hotel dining chairs, and the finishing side is in finish cure time and shipping.
How to plan
Work back from the opening date: installation 5 days, shipping 25–30, production 30, sample 15. That is about 11 weeks, and any plan shorter than that is buying air freight.
This is the second section of the buying guide, with rush orders and air freight and delivery window versus lead time as the two notes that follow.
The workshop that runs those six stages is described under hotel furniture factory.