Craft Notes
Home · Workshop

The bottleneck is never the machine, it is the queue in front of it

A 25-day lead time is four days of work and twenty-one days of waiting, in the wrong places.

31 Dec 2026 · Workshop
The guide behind thisThe workshop guide: kiln, jigs, QC and packing — The five checks that catch a bad batch before it ships, and the order the work actually moves through a furniture factory.

Where the queue sits

Finishing, most often. two-pack polyurethane, 3 coats, 30–40 micron dry film, 24 h between coats One booth serving four assembly lines is a queue, and the queue is the lead time.

The stage breakdown is in lead time stages, and the scheduling side is in capacity per month.

What balancing means

Adding a second booth, not a second CNC. The machine that runs at 60% is not the constraint, whatever the operator says.

Shops that run two finishing lines are on hotel furniture factory, and the booth detail is in spray booth and finishing.

The batch size

Small batches at the bottleneck make it worse, not better. Run one colour for two days rather than four colours in one, and the queue shortens.

This is in the workshop guide, with production slots and booking as the note on who gets the booth first.

Booth capacity is the number to ask about, and the workshop is described in hotel furniture Foshan.